DEVELOPMENT PLAN

THE NJWP IS BEING DEVELOPED IN PHASES OVER AN APPROXIMATELY 7-8 YEAR PERIOD.

 PHASE 1:

Phase 1 construction commenced in 2021 and is comprised of:

  • An approximately 30–35-acre property and adjacent wharf infrastructure purpose-built for marshalling (i.e., wind turbine staging, final assembly, and transport) (Parcel A);
  • A dredged access channel from the NJWP to the main Delaware River shipping channel, as well as berth pockets and a turning basin able to accommodate jack-up installation vessels and other turbine installation and delivery vessels;
  • Two inland Tier 1 turbine component manufacturing Parcels (Parcels C and G), connected to the wharf via a heavy-haul road corridor purpose-built for moving components such as nacelles and towers;
  • An approximately 25-acre confined disposal facility (CDF) for dredge material management (Parcel E);
  • An approximately 4-acre property for general port administration and parking (Parcel D); and
  • On-site utility infrastructure and grid connections.

Parcel A completed in Quarter 2 of 2024, with the balance of Phase 1 anticipated to complete over the period 2025-2026.

PHASE 1:

Phase 1, which is under construction, will be comprised of:

  • An approximately 30-acre property and adjacent wharf infrastructure purpose-built for marshalling (i.e., wind turbine staging, final assembly, and transport) (“Parcel A”);
  • Dredging of an access channel from the NJWP to the main Delaware River shipping channel, as well as berth pockets able to accommodate jack-up installation vessels;
  • Over 50 acres of property purpose-built for Tier 1 wind manufacturing, connected to the wharf via a heavy haul road corridor (“Parcel C” and “Parcel G”);
  • An approximately 30-acre confined disposal facility for dredge placement (“Parcel E”);
  • An approximately 5-acre property for general port administration and parking (“Parcel D); and
  • On-site utility (power, water, sewer, telecommunications) infrastructure and grid connections.

Parcel A is targeted to be completed in Quarter 2 of 2024, with the balance of Phase 1 anticipated to complete over the period 2024-2025.

PHASE 2:

Phase 2 of the project, which is currently at an early design stage, will comprise:

  • An approximately 30-35-acre property and adjacent wharf infrastructure purpose-built for marshalling with dredged berth pockets (Parcel B1);
  • An approximately 46-56-acre property purpose-built for Tier 1 turbine component manufacturing, as well as adjacent wharf infrastructure and dredged berth pocket (Parcel B2), with the potential to be further expanded;1
  • On-site utility infrastructure; and
  • Heavy-haul road corridors connecting Parcels and shared wharves.

Development of Phase 2 is targeted to commence in early 2024 and to achieve completion by 2029*.

 

*All development timelines are subject to change dependent upon the State of New Jersey’s Offshore Wind strategy and market demands

 

 

 

PHASE 2:

Phase 2 of the project, which is currently at an early design stage, will comprise:

  • An approximately 30-35-acre property and adjacent wharf infrastructure purpose-built for marshalling with dredged berth pockets (Parcel B1);
  • An approximately 46-56-acre property purpose-built for Tier 1 turbine component manufacturing, as well as adjacent wharf infrastructure and dredged berth pocket (Parcel B2), with the potential to be further expanded;1
  • On-site utility infrastructure; and
  • Heavy-haul road corridors connecting Parcels and shared wharves.

Development of Phase 2 is targeted to commence in early 2024 and to achieve completion by *2029.

 

*All development timelines are subject to change dependent upon the State of New Jersey’s Offshore Wind strategy and market demands